Funded by the 9th EDF, Windward Roads executed the infrastructure in the "Under the Hill" area.
This project entailed the excavation and road construction on a steep hillside.
Retaining walls in traditional rock work were build together with foundations and cisterns for the future housing project.
The construction of a grey water tank and the extension of a water catchment in The Bottom were part of the scope of works.

Client:
SONA
(Stichting Ontwikkeling Nederlandse Antillen)


Financed by:
European Union
(European Development Fund)


Design:
CEC-Windward N.V.

Coordination:
USONA
Independent Consulting Engineers N.V.


Construction Period:
2010-2011

Project Duration:
18 months

Project Facts:
  • 250 m3 grey water tank
  • 350 m2 water catchment extension
  • 10 pc house foundation & cisterns
  • 4700 m3 groundworks
  • 650 m3 rockwall